Total Installed Capacity: 47.4 MW
Galip Hoca GPP, which was established within the borders of Germencik district of Aydın province, started operation on 02.04.2009.
Total Installed Capacity: 114.9 MW
EFELER GPP, established within the borders of Germencik and Incirliova districts of Aydın province, consists of 4 units. EFE1 GPP was commissioned on 26.08.2015, EFE2 GPP on 01.10.2014, EFE3 GPP on 06.03.2015 and EFE 4 GPP on 03.07.2015.
Total Installed Capacity: 212.5 MW
EFE 6 GPP, which was established within the borders of Germencik district of Aydın province, started operation on 20.08.2017.
Total Installed Capacity: 212.5 MW
EFE 7 GPP 25 MW, which was established within the borders of Germencik district of Aydın province, started operation on 12.10.2018.
Total Installed Capacity: 212.5 MW
The first unit of EFE 8 GPP, which was established within the borders of Germencik district of Aydın province, started operation on 26.12.2020 and the second unit started operation on 24.12.2021.